Glenwood Caverns Look what's going up! Grand MID-MARCH 2019 Upper drive terminal assembly begins . Base Terminal retaining walls . Power infrastructure installation Bases for new towers complete Begin base terminal assembly Utility conduit installation starts New foundation for upper terminal done - Steel framework assembly started New tower pads set . Old cable & cabins down Upper and lower terminals removed . New foundation begun Follow the NEW GONDOLA progress : at GlenwoodCaverns.com & on Facebook!